Construction Plans & Updates
Timeline: Next Steps
2018-19
- Facilities Plan - stakeholder input
- May 14, 2019 - Facilities bond referendum passed
2019-20
- Architectural drawings completed for middle schools and Carver by Fall 2019
- Construction begins in Spring 2020
2020-21
- Construction continues, new elementary schools designed and out for bid
- Boundary study underway
- Design work begins for high school renovation
2021-22
- Construction continues on elementary and middle school sites
- High school construction begins
2022-23
- New and renovated elementary and middle schools open
- New boundaries take effect
- High school construction continues
2023-24
- High school construction final phase
See more about Facilities Plan Phase I, Facilities Plan Phase II, or Facilities Plan Phase III by visiting those web pages.