• Construction Plans & Updates


    Timeline: Next Steps

    2018-19

    • Facilities Plan - stakeholder input
    • May 14, 2019 - Facilities bond referendum passed

    2019-20

    • Architectural drawings completed for middle schools and Carver by Fall 2019
    • Construction begins in Spring 2020

    2020-21

    • Construction continues, new elementary schools designed and out for bid
    • Boundary study underway
    • Design work begins for high school renovation

    2021-22

    • Construction continues on elementary and middle school sites
    • High school construction begins

    2022-23

    • New and renovated elementary and middle schools open
    • New boundaries take effect
    • High school construction continues

    2023-24

    • High school construction final phase 

    See more about Facilities Plan Phase I,  Facilities Plan Phase II, or Facilities Plan Phase III by visiting those web pages.